QUALITY ASSURANCE PLAN

Plastic Valve Standard

Quality Assurance Plan for Solid Plastic Valves — covering polymer raw material, finished product hydrostatic testing, and final document/marking verification.

About This QAP

Our complete Quality Assurance & Control procedure for solid Thermoplastic Valves (PP / PPH / PVDF / ISO.PP) — from polymer grade verification and stem chemical analysis through hydrostatic body and seat leak testing, dimensional inspection, and final document and marking verification before dispatch.

Quality Assurance Plan — Plastic Valves

SR.NO ITEMS PARAMETER TYPE OF CHECK QUANTUM REFERENCE DOC. & ACCEPTANCE NORMS FORMAT / RECORD UNP SCOPE TPIA / CUSTOMER
PWRWR
1. Raw Material — (A) Non-Metallic Parts, (B) Metallic Parts
APolymer (PP / PPH / PVDF / ISO.PP)IntactnessVisual100%P.O. Specification & Product Data SheetsSupplier MTC / COC
Grade ConfirmationVisual100%Product Data SheetsSupplier MTC / COC
Physical VerificationVisual100%Product Data SheetsSupplier MTC / COC
BStem (Major Parts)Chemical (per approved GAD / QAP / PO Spec) — Major ElementsChemical Analysis1 Sample / Size / Heat or per POManufacturer / Supplier TC or NABL Lab TCTC
2. Finished Products — Plastic Valves
2.1Plastic ValvesLeakage Test (Body & Seat)Hydrostatic Test100%Hydro Test Procedure or Approved GADFinal Insp. Report✓ (10%)
Dimensions, WorkmanshipMeasurement, Visual100%Approved GAD / UNP As-Built DrawingFinal Insp. Report✓ (10%)
3. Final Inspection
3.1Plastic ValvesDocuments VerificationReview of Material Stamping & Issue of IRN100%Approved Drawing / POIR
Marking & TaggingVisual100%Approved DrawingIR

Legend

P
PerformUNP Action
W
WitnessObserve Test
R
ReviewDocument Check

Notes

Customer & Inspection Notes

  • The above QAP is our internal procedure of Quality Assurance & Control.
  • We provide our Final Inspection Report & MTC or COC to Customers.
  • Based on Inspection Report we allow our customer to check the following:
  1. Physical Verification of Valves & Quantity Check
  2. Witnessing a leakage Test (Hydro Test) as per our Standard Test Procedure & pressure rating confirmed per QAP Scope
  3. Dimension Check of final assembly of Valve as per our standard or as-built drawings